What is required for soil stockpiles and other disturbed areas that will remain inactive for more than 14 days?

  1. Complete removal

  2. Temporary stabilization

  3. Permanent sealing

  4. Unmonitored placement

The correct answer is: Temporary stabilization

For soil stockpiles and other disturbed areas that will remain inactive for more than 14 days, temporary stabilization is required. This action is critical to prevent erosion and sediment runoff, which can significantly contribute to water pollution. Temporary stabilization typically involves covering the disturbed area with vegetation, mulch, or soil stabilization materials to protect the soil from rainfall and wind erosion while it remains inactive. The importance of this measure lies in the need to maintain soil integrity and minimize the potential for sediment to enter waterways, thereby adhering to regulations designed for stormwater management. Implementing temporary stabilization practices helps to ensure that any exposed soil does not lose its nutrients or manage stormwater runoff effectively during the period of inactivity. This form of environmental stewardship helps to safeguard the surrounding ecosystem and comply with the requirements of a Storm Water Pollution Prevention Plan (SWPPP).